Bryan Laidlaw

Heating Engineer

Balgreen
Primary School

Balgreen
Primary School

The Balgreen contract involved a full system drain down, stripping out the existing one pipe system and existing cast iron radiators. We then installed a new 2 pipe system with the mains in the corridors, valved branches to feed each classroom and new Stelrad radiators throughout the school. The job was carried out over the school summer holiday period.

What I
Worked On

  • Stripping Out Existing Pipework
  • Stripping Out Cast Iron Radiators
  • Fitting New Pipework Mains Throughout The School
  • Hang An Valve New Stelrad Radiators
  • Fit Classroom Pipework & New Stelrad Radiators