Bryan Laidlaw

Heating Engineer

Edinburgh
Art College

Edinburgh
Art College

The Edinburgh art college was a 2 year project completed over 2 phases. The first phase of the contract comprised of a full system strip out and new heating system installation. The new installation involved fitting a rooftop plantroom, 3 air handling units, new heating mains pipework, radiator circuits and all new radiators.

What I
Worked On

  • phase 1
  • Welding Of The Heating System Mains
  • Fitting The Rooftop Air Handling Unit
  • Fitting The 3 Internal Air Handling Units
  • Fitting Radiators & Associated Pipework Runs

Me Doing A Bit Welding

What I
Worked On

Throughout the project I was the main welder. Phase 2 involved the prefabrication of all the boilerhouse pipework off site. Pipe sizes ranged from 12 inch down to 2 1/2 inch. Upon completion the prefabricated sections were assembled in the boilerhouse and piped up to the new plant.

  • phase 2
  • Welding Of All Prefabricated Sections For The New Boilerhouse
  • Fitting 4 Pump Sets
  • Fitting A Plate Heat Exchanger
  • Fitting 5 Pressure Vessels & The Press Unit
  • Piping The Primary Side Of The Domestic Cylinders
  • Testing Of The Boilerhouse Pipework

6 Inch Welded Hot Pass

Once the boilerhouse installation was complete it was tested to 7 bar, commissioned and fired up without any problems.