The Murrayburn contract initially involved a complete system drain down and cutting in of ball valves, for future isolation of phased works. After this we then fitted a new 2 pipe heating mains in the corridors along with anchors and expansion bellows. 

Once the mains runs were complete it was a case of isolating the phase to be worked on ( 2 classrooms per phase ), drain down, strip out the existing radiator pipework, re-pipe to the existing cast radiators, connect to the new 2 pipe mains, test and make the phase live. When a phase was finished I'd then prefabricate the pipework sizes ready for the next 2 classrooms. There were 15 radiators to each phase and the work took about 1 week per phase from start to finish.

What I
Worked On

  • Drain Down & Cut In Valves for Future Connection
  • Strip Out Old Pipework Mains
  • Run New Heating Mains Throughout The School
  • Drain Down & Strip Out Classroom 1 Pipe System
  • Fitted New 2 Pipe System To Existing Cast Iron Radiators
  • Test The New Pipework & Make The Classrooms Live